After the old and new tanks were set up, the tilers were ready to get to work. In the new fermentation cellar, steam boiler room, workshop, spare parts store and in the passage to the fermenting cellar, the floor was laid with hexagonal tiles. It was laid as a vibrating floor in dry screed, then sealed with epoxy resin. This makes the floor extremely durable and resistant to chemicals, which is particularly important in a brewery.
In addition, the social rooms on the first floor of the inner extension were expanded, power cables and water pipes (for the social rooms) were laid, radiators and toilets were installed. And for a clear view, wide windows have also been built in.